What Ontario's connection assessments actually establish: the assessed station quantities behind the province's largest new industrial loads, the capacities the planning record publishes, and the reconciliations the process itself performs

The engineering layer of Ontario's connection process: final System Impact Assessment reports for the province's flagship new loads (the Windsor battery plant connection, the St. Thomas plant's new station, the Algoma Steel electric-arc-furnace staging, a Toronto data centre, the existing Dofasco station), the planning record's published local capacities (a shared station capacity with two named claimants; a circuit pair assessed across two vintages), and the issuer's own published reconciliations of firm and potential load against total capability. Every quantity is the issuer's own stated figure, quoted from the archived document; nothing is summed, allocated, or inferred.

A Resolution record holds one institution's own published figures for a single, specific quantity — a projection, an estimate, or a measured record — across every vintage in which that institution restated it. Each time an issuer publishes a new budget, report, or release, an earlier figure does not disappear from the record; it is preserved exactly as it was first published, dated and cited, alongside the newer one. What is a Resolution record? →

Maintained record. This lineage preserves an official record version by version — observations, estimates, or benchmarks its issuer restated over time. It projects nothing, so no settlement is pending; where a figure can still be revised, the page says so. How the numbers moved between versions is the evidence this lineage exists to keep.

The lineage

VintageIssuerPublishedPositionSource
Final Report of 2023-07-10, captured 2026-08-03Independent Electricity System Operator2023-07-10currentSource → · accessed 2026-08-03
Final Report of 2023-04-21, captured 2026-08-03Independent Electricity System Operator2023-04-21currentSource → · accessed 2026-08-03
Final Report of 2024-06-12, captured 2026-08-03Independent Electricity System Operator2024-06-12currentSource → · accessed 2026-08-03
Final Report of 2025-06-12, captured 2026-08-03Independent Electricity System Operator2025-06-12currentSource → · accessed 2026-08-03
Final Report of 2024-10-16, captured 2026-08-03Independent Electricity System Operator2024-10-16currentSource → · accessed 2026-08-03
Final Report of 2021-06-10, captured 2026-08-03Independent Electricity System Operator2021-06-10currentSource → · accessed 2026-08-03
Final Report of 2019-09-12, captured 2026-08-03 — superseded on the aggregate-load finding by the 2020 addendumIndependent Electricity System Operator2019-09-12supersededSource → · accessed 2026-08-03
Addendum of 2020-11-17, captured 2026-08-03 — the governing vintage for the aggregate-load findingIndependent Electricity System Operator2020-11-17currentSource → · accessed 2026-08-03
Report of 2024-04-18, captured 2026-08-03Independent Electricity System Operator2024-04-18currentSource → · accessed 2026-08-03
Report of 2020-07-17, captured 2026-08-03Hydro One Networks Inc.2020-07-17currentSource → · accessed 2026-08-03
Report of 2024-12-18, captured 2026-08-03Independent Electricity System Operator2024-12-18currentSource → · accessed 2026-08-03
Final Addendum Report of 2025-06-30, captured 2026-08-04Independent Electricity System Operator2025-06-30supersededSource → · accessed 2026-08-04
Final Addendum 2 Report of 2026-02-04, captured 2026-08-04 — the governing vintage for the three-station requirementIndependent Electricity System Operator2026-02-04currentSource → · accessed 2026-08-04
VintagePeriodValueRoleAssuranceBasis
Final Report of 2023-07-10, captured 2026-08-03Final connection assessment of 2023-07-10 — the assessed station maximum for the Windsor battery-plant station (CAA 2022-726)150.0 MWinstitutional estimate
Final Report of 2023-04-21, captured 2026-08-03Final connection assessment of 2023-04-21 — Algoma Steel EAF Stage 1 (CAA 2021-694/695)140.0 MWinstitutional estimate
Final Report of 2024-06-12, captured 2026-08-03Final connection assessment of 2024-06-12 — Algoma Steel EAF Stage 2B (CAA 2023-768)250.0 MWinstitutional estimate
Final Report of 2024-06-12, captured 2026-08-03Final connection assessment of 2024-06-12 — the regional interface transfer limit stated in the Stage 2B assessment700.0 MWinstitutional estimate
Final Report of 2025-06-12, captured 2026-08-03Final connection assessment of 2025-06-12 — Algoma Steel EAF Stage 3, the facility's full assessed level (CAA 2024-787)300.0 MWinstitutional estimate
Final Report of 2024-10-16, captured 2026-08-03Final connection assessment of 2024-10-16 — the Toronto data centre's ultimate load (CAA 2024-795)80.0 MWinstitutional estimate
Final Report of 2021-06-10, captured 2026-08-03Final connection assessment of 2021-06-10 — the existing Dofasco station's assessed one-time increase (CAA 2021-693)214.0 MWinstitutional estimate
Final Report of 2019-09-12, captured 2026-08-03 — superseded on the aggregate-load finding by the 2020 addendumFinal connection assessment of 2019-09-12 — the stated load-security criterion for the Leamington-area circuit pair (CAA 2018-633)600.0 MWinstitutional estimate
Final Report of 2019-09-12, captured 2026-08-03 — superseded on the aggregate-load finding by the 2020 addendumFinal connection assessment of 2019-09-12 — load along the corridor interruptible by configuration at the 2019 vintage (CAA 2018-633)567.0 MWinstitutional estimate
Addendum of 2020-11-17, captured 2026-08-03 — the governing vintage for the aggregate-load findingAddendum of 2020-11-17 — the restated interruptible-load aggregate at the 2020 vintage (CAA 2018-633 Addendum 1)608.0 MWinstitutional estimate
Report of 2024-04-18, captured 2026-08-03Central-West Bulk Plan of 2024-04-18 — firm load in the London area, as the issuer states it620.0 MWinstitutional estimate
Report of 2024-04-18, captured 2026-08-03Central-West Bulk Plan of 2024-04-18 — potential load beyond the firm load, as the issuer states it300.0 MWinstitutional estimate
Report of 2024-04-18, captured 2026-08-03Central-West Bulk Plan of 2024-04-18 — the issuer's own stated total of firm plus potential load ('900 MW in total')900.0 MWinstitutional estimate
Report of 2020-07-17, captured 2026-08-03Needs Assessment of 2020-07-17 — Port Arthur TS #1 station capacity after the low-voltage yard refurbishment, two named supplied parties, no published split59.0 MWinstitutional estimate
Report of 2024-12-18, captured 2026-08-03Burlington to Nanticoke IRRP of 2024-12-18 — data-centre connection interest in the Caledonia-Norfolk subregion that the IRRP states its own forecast does not capture700.0–1,700.0 MWinstitutional estimate
Final Addendum Report of 2025-06-30, captured 2026-08-04Final addendum of 2025-06-30 — the three-station total the applicant was required to stay below (CAA 2024-795)400.0 MWinstitutional estimate
Final Addendum 2 Report of 2026-02-04, captured 2026-08-04 — the governing vintage for the three-station requirementFinal Addendum 2 of 2026-02-04 — the same three-station total, now a real-time switching threshold (CAA 2024-795)400.0 MWinstitutional estimate
Final Addendum 2 Report of 2026-02-04, captured 2026-08-04 — the governing vintage for the three-station requirementFinal Addendum 2 of 2026-02-04 — the data centre's own ultimate load, restated unchanged (CAA 2024-795)80.0 MWinstitutional estimate

Movement between vintages

A record, not a ranking: this entry states what was published and how it compares to what followed. It never says who was right, which institution performed better, or grades a forecaster's competence.

ComparisonCompared vintagesMovementBasis
One circuit pair, two assessment vintages: the 2019 interruptible-load finding against the 2020 restatementFinal Report of 2019-09-12, captured 2026-08-03 — superseded on the aggregate-load finding by the 2020 addendum (institutional estimate 567.0 MW) vs. Addendum of 2020-11-17, captured 2026-08-03 — the governing vintage for the aggregate-load finding (institutional estimate 608.0 MW)+41.0 MWsame issuer
One three-station limit, two assessment vintages: a build obligation replaced by a switching instructionFinal Addendum Report of 2025-06-30, captured 2026-08-04 (institutional estimate 400.0 MW) vs. Final Addendum 2 Report of 2026-02-04, captured 2026-08-04 — the governing vintage for the three-station requirement (institutional estimate 400.0 MW)not comparable — The two figures are identical and the obligations attached to them are not. A numeric difference of zero would state that nothing changed between the vintages; what changed is what the number requires — from building capacity to stay below it, to switching a breaker when it is crossed.same issuer
Evidence qualifications (6)
Latest source: What Ontario's connection assessments actually establish: the assessed station quantities behind the province's largest new industrial loads, the capacities the planning record publishes, and the reconciliations the process itself performs · accessed 2026-08-03

Related on this site

A record, not a ranking: this entry states what was published and how it compares to what followed. It never says who was right, which institution performed better, or grades a forecaster's competence.

This is the current public record for this lineage. See Work with Countability for a commissioned projection-resolution question.