Resolution
Canada Energy RegulatorclimateAwaiting settlementCurrent

The Canada Energy Regulator's Energy Future 2026 electricity projections: what every scenario assumes about generation and capacity to 2035 and 2050, held beside the dataset's own recorded history

Canada's electricity generation (gigawatt hours) and installed generating capacity (megawatts), as the Canada Energy Regulator's 'Canada's Energy Future 2026: Energy Supply and Demand Projections to 2050' dataset states them -- the recorded history the dataset itself carries (2005 through 2023, identical across scenarios at 2023) and the four scenarios' modelled levels at 2035 and 2050. The issuer's own scenario definitions name Canadian GDP growth, LNG exports, data centre load growth, and global oil and natural gas prices as the drivers its Higher and Lower scenarios bracket.

A Resolution record follows one institution's figures for a defined quantity. It may contain projections, estimates or measured observations. Each version held here keeps its publication date and source, so a newer figure does not erase the earlier one. What is a Resolution record? →

Awaiting settlement. This record contains forward-looking positions. No audited or final outcome has yet settled the projections; any interim estimate is identified below. Conditional scenarios describe pathways under stated assumptions and are not predictions.

The lineage

VintageIssuerPublishedPositionSource
EF2026 / Current MeasuresCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Current MeasuresCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Current MeasuresCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Current MeasuresCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2010)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Canada Net-zeroCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / recorded history (block-invariant from 2005)Canada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Lower ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
EF2026 / Higher ScenarioCanada Energy Regulator2026-03-16currentSource → · accessed 2026-07-17
VintagePeriodValueRoleAssuranceBasis
EF2026 / Current Measures2005 (recorded history)594,750.5 GWhinstitutional estimate——
EF2026 / Current Measures2023 (last recorded history year; identical across all four scenarios)621,540.0 GWhinstitutional estimate——
EF2026 / Current Measures2025, Current Measures scenario (modelled year)651,483.6 GWhscenario——
EF2026 / Current Measures2035, Current Measures scenario800,194.9 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario871,670.3 GWhscenario——
EF2026 / Higher Scenario2035, Higher scenario860,382.8 GWhscenario——
EF2026 / Lower Scenario2035, Lower scenario756,146.3 GWhscenario——
EF2026 / Current Measures2050, Current Measures scenario974,993.2 GWhscenario——
EF2026 / Canada Net-zero2050, Canada Net-zero scenario1,323,010.3 GWhscenario——
EF2026 / Current Measures2010 (recorded history)567,389.1 GWhinstitutional estimate——
EF2026 / Current Measures2022 (recorded history)647,380.7 GWhinstitutional estimate——
EF2026 / Current Measures2005 (recorded history)121,968.6 MWinstitutional estimate——
EF2026 / Current Measures2011 (recorded history)122,968.3 MWinstitutional estimate——
EF2026 / Current Measures2023 (last recorded history year; identical across all four scenarios)159,363.1 MWinstitutional estimate——
EF2026 / Current Measures2035, Current Measures scenario225,810.4 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario252,433.3 MWscenario——
EF2026 / Higher Scenario2035, Higher scenario244,754.9 MWscenario——
EF2026 / Lower Scenario2035, Lower scenario217,421.8 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2011 (Newfoundland and Labrador: recorded history)41,703.5 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Newfoundland and Labrador: last recorded history year; identical across all four scenarios)44,292.7 GWhinstitutional estimate——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Newfoundland and Labrador: the lowest of the four scenario levels)99,958.1 GWhscenario——
EF2026 / Higher Scenario2035, Higher scenario (Newfoundland and Labrador: the highest of the four scenario levels)108,769.6 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Newfoundland and Labrador: recorded history)7,720.9 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2011 (Newfoundland and Labrador: recorded history)7,389.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Newfoundland and Labrador: last recorded history year; identical across all four scenarios)8,783.3 MWinstitutional estimate——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Newfoundland and Labrador: the lowest of the four scenario levels)22,785.6 MWscenario——
EF2026 / Higher Scenario2035, Higher scenario (Newfoundland and Labrador: the highest of the four scenario levels)24,396.8 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2010 (Prince Edward Island: recorded history)462.6 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2022 (Prince Edward Island: recorded history)534.6 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Prince Edward Island: last recorded history year; identical across all four scenarios)557.1 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Prince Edward Island: the lowest of the four scenario levels)1,055.5 GWhscenario——
EF2026 / Higher Scenario2035, Higher scenario (Prince Edward Island: the highest of the four scenario levels)1,595.9 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Prince Edward Island: recorded history)175.6 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2017 (Prince Edward Island: recorded history)350.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Prince Edward Island: last recorded history year; identical across all four scenarios)351.9 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Prince Edward Island: the lowest of the four scenario levels)640.2 MWscenario——
EF2026 / Higher Scenario2035, Higher scenario (Prince Edward Island: the highest of the four scenario levels)843.7 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2011 (Nova Scotia: recorded history)11,731.6 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Nova Scotia: last recorded history year; identical across all four scenarios)9,058.5 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Nova Scotia: the lowest of the four scenario levels)17,339.5 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Nova Scotia: the highest of the four scenario levels)29,213.5 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Nova Scotia: recorded history)2,381.5 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2011 (Nova Scotia: recorded history)2,368.1 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Nova Scotia: last recorded history year; identical across all four scenarios)3,111.6 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Nova Scotia: the lowest of the four scenario levels)7,245.2 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Nova Scotia: the highest of the four scenario levels)11,896.8 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2011 (New Brunswick: recorded history)11,804.4 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (New Brunswick: last recorded history year; identical across all four scenarios)13,895.8 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (New Brunswick: the lowest of the four scenario levels)13,046.3 GWhscenario——
EF2026 / Higher Scenario2035, Higher scenario (New Brunswick: the highest of the four scenario levels)13,717.4 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (New Brunswick: recorded history)4,234.5 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2010 (New Brunswick: recorded history)3,745.3 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2022 (New Brunswick: recorded history)4,535.3 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (New Brunswick: last recorded history year; identical across all four scenarios)4,509.4 MWinstitutional estimate——
EF2026 / Current Measures2035, Current Measures scenario (New Brunswick: the lowest of the four scenario levels)4,740.6 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (New Brunswick: the highest of the four scenario levels)5,278.7 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2010 (Quebec: recorded history)180,609.9 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2022 (Quebec: recorded history)215,544.1 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Quebec: last recorded history year; identical across all four scenarios)195,507.7 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Quebec: the lowest of the four scenario levels)214,279.2 GWhscenario——
EF2026 / Higher Scenario2035, Higher scenario (Quebec: the highest of the four scenario levels)237,212.4 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Quebec: recorded history)39,258.7 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2017 (Quebec: recorded history)45,369.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Quebec: last recorded history year; identical across all four scenarios)46,900.1 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Quebec: the lowest of the four scenario levels)53,707.1 MWscenario——
EF2026 / Higher Scenario2035, Higher scenario (Quebec: the highest of the four scenario levels)57,723.2 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2010 (Ontario: recorded history)135,412.9 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2022 (Ontario: recorded history)157,953.7 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Ontario: last recorded history year; identical across all four scenarios)158,135.3 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Ontario: the lowest of the four scenario levels)156,081.3 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Ontario: the highest of the four scenario levels)201,723.9 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Ontario: recorded history)31,454.5 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2010 (Ontario: recorded history)28,475.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2022 (Ontario: recorded history)44,183.9 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Ontario: last recorded history year; identical across all four scenarios)43,355.6 MWinstitutional estimate——
EF2026 / Current Measures2035, Current Measures scenario (Ontario: the lowest of the four scenario levels)48,357.1 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Ontario: the highest of the four scenario levels)54,977.3 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2010 (Manitoba: recorded history)33,713.4 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2022 (Manitoba: recorded history)37,854.2 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Manitoba: last recorded history year; identical across all four scenarios)33,373.7 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Manitoba: the lowest of the four scenario levels)29,552.1 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Manitoba: the highest of the four scenario levels)36,398.8 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Manitoba: recorded history)5,593.6 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2010 (Manitoba: recorded history)5,583.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2022 (Manitoba: recorded history)6,741.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Manitoba: last recorded history year; identical across all four scenarios)6,554.0 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Manitoba: the lowest of the four scenario levels)6,919.8 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Manitoba: the highest of the four scenario levels)8,500.5 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2010 (Saskatchewan: recorded history)20,407.4 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2022 (Saskatchewan: recorded history)24,516.0 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Saskatchewan: last recorded history year; identical across all four scenarios)24,900.9 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Saskatchewan: the lowest of the four scenario levels)23,673.2 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Saskatchewan: the highest of the four scenario levels)29,493.3 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Saskatchewan: recorded history)3,733.3 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2010 (Saskatchewan: recorded history)4,186.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2022 (Saskatchewan: recorded history)5,628.5 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Saskatchewan: last recorded history year; identical across all four scenarios)5,275.0 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Saskatchewan: the lowest of the four scenario levels)6,691.7 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Saskatchewan: the highest of the four scenario levels)9,997.4 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2011 (Alberta: recorded history)72,813.6 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (Alberta: last recorded history year; identical across all four scenarios)84,133.9 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Alberta: the lowest of the four scenario levels)96,288.6 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Alberta: the highest of the four scenario levels)116,135.3 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (Alberta: recorded history)11,998.1 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2011 (Alberta: recorded history)13,019.9 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (Alberta: last recorded history year; identical across all four scenarios)21,006.3 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (Alberta: the lowest of the four scenario levels)33,459.8 MWscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (Alberta: the highest of the four scenario levels)45,201.3 MWscenario——
EF2026 / recorded history (block-invariant from 2010)2010 (British Columbia: recorded history)60,281.4 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2022 (British Columbia: recorded history)70,681.6 GWhinstitutional estimate——
EF2026 / recorded history (block-invariant from 2010)2023 (British Columbia: last recorded history year; identical across all four scenarios)56,165.9 GWhinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (British Columbia: the lowest of the four scenario levels)97,905.2 GWhscenario——
EF2026 / Canada Net-zero2035, Canada Net-zero scenario (British Columbia: the highest of the four scenario levels)114,114.3 GWhscenario——
EF2026 / recorded history (block-invariant from 2005)2005 (British Columbia: recorded history)15,047.5 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2011 (British Columbia: recorded history)15,123.0 MWinstitutional estimate——
EF2026 / recorded history (block-invariant from 2005)2023 (British Columbia: last recorded history year; identical across all four scenarios)18,985.8 MWinstitutional estimate——
EF2026 / Lower Scenario2035, Lower scenario (British Columbia: the lowest of the four scenario levels)31,593.0 MWscenario——
EF2026 / Higher Scenario2035, Higher scenario (British Columbia: the highest of the four scenario levels)39,903.5 MWscenario——

Movement between vintages

This record shows what an institution published and how its figures compare across versions or with later outcomes. It does not rank institutions or grade their forecasting ability.

ComparisonCompared vintagesMovementBasis
Generation, recorded 2023 to Current Measures 2025 (the scenario's own near-term path)EF2026 / Current Measures (institutional estimate 621,540.0 GWh) vs. EF2026 / Current Measures (scenario 651,483.6 GWh)+29,943.6 GWhsame issuer
Generation, recorded 2023 to Current Measures 2035EF2026 / Current Measures (institutional estimate 621,540.0 GWh) vs. EF2026 / Current Measures (scenario 800,194.9 GWh)+178,654.9 GWhsame issuer
Generation, recorded 2023 to Canada Net-zero 2035EF2026 / Current Measures (institutional estimate 621,540.0 GWh) vs. EF2026 / Canada Net-zero (scenario 871,670.3 GWh)+250,130.3 GWhsame issuer
Generation, recorded 2023 to Higher scenario 2035EF2026 / Current Measures (institutional estimate 621,540.0 GWh) vs. EF2026 / Higher Scenario (scenario 860,382.8 GWh)+238,842.8 GWhsame issuer
Generation, recorded 2023 to Lower scenario 2035EF2026 / Current Measures (institutional estimate 621,540.0 GWh) vs. EF2026 / Lower Scenario (scenario 756,146.3 GWh)+134,606.3 GWhsame issuer
Capacity, recorded 2023 to Current Measures 2035EF2026 / Current Measures (institutional estimate 159,363.1 MW) vs. EF2026 / Current Measures (scenario 225,810.4 MW)+66,447.3 MWsame issuer
Capacity, recorded 2023 to Canada Net-zero 2035EF2026 / Current Measures (institutional estimate 159,363.1 MW) vs. EF2026 / Canada Net-zero (scenario 252,433.3 MW)+93,070.2 MWsame issuer
Capacity, recorded 2023 to Higher scenario 2035EF2026 / Current Measures (institutional estimate 159,363.1 MW) vs. EF2026 / Higher Scenario (scenario 244,754.9 MW)+85,391.8 MWsame issuer
Capacity, recorded 2023 to Lower scenario 2035EF2026 / Current Measures (institutional estimate 159,363.1 MW) vs. EF2026 / Lower Scenario (scenario 217,421.8 MW)+58,058.7 MWsame issuer
Generation, the fastest twelve-year stretch in the recorded history (2010 to 2022)EF2026 / Current Measures (institutional estimate 567,389.1 GWh) vs. EF2026 / Current Measures (institutional estimate 647,380.7 GWh)+79,991.6 GWhsame issuer
Capacity, the fastest twelve-year stretch in the recorded history (2011 to 2023)EF2026 / Current Measures (institutional estimate 122,968.3 MW) vs. EF2026 / Current Measures (institutional estimate 159,363.1 MW)+36,394.8 MWsame issuer
Generation, Newfoundland and Labrador: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 41,703.5 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 44,292.7 GWh)+2,589.2 GWhsame issuer
Capacity, Newfoundland and Labrador: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 7,389.0 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 8,783.3 MW)+1,394.3 MWsame issuer
Generation, Prince Edward Island: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 462.6 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 534.6 GWh)+72.0 GWhsame issuer
Capacity, Prince Edward Island: the fastest twelve-year stretch in its own record (2005 to 2017)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 175.6 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 350.0 MW)+174.4 MWsame issuer
Generation, Nova Scotia: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 11,731.6 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 9,058.5 GWh)-2,673.1 GWhsame issuer
Capacity, Nova Scotia: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 2,368.1 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 3,111.6 MW)+743.5 MWsame issuer
Generation, New Brunswick: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 11,804.4 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 13,895.8 GWh)+2,091.4 GWhsame issuer
Capacity, New Brunswick: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 3,745.3 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 4,535.3 MW)+790.0 MWsame issuer
Generation, Quebec: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 180,609.9 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 215,544.1 GWh)+34,934.2 GWhsame issuer
Capacity, Quebec: the fastest twelve-year stretch in its own record (2005 to 2017)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 39,258.7 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 45,369.0 MW)+6,110.3 MWsame issuer
Generation, Ontario: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 135,412.9 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 157,953.7 GWh)+22,540.8 GWhsame issuer
Capacity, Ontario: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 28,475.0 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 44,183.9 MW)+15,708.9 MWsame issuer
Generation, Manitoba: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 33,713.4 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 37,854.2 GWh)+4,140.8 GWhsame issuer
Capacity, Manitoba: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 5,583.0 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 6,741.0 MW)+1,158.0 MWsame issuer
Generation, Saskatchewan: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 20,407.4 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 24,516.0 GWh)+4,108.6 GWhsame issuer
Capacity, Saskatchewan: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 4,186.0 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 5,628.5 MW)+1,442.5 MWsame issuer
Generation, Alberta: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 72,813.6 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 84,133.9 GWh)+11,320.3 GWhsame issuer
Capacity, Alberta: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 13,019.9 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 21,006.3 MW)+7,986.4 MWsame issuer
Generation, British Columbia: the fastest twelve-year stretch in its own record (2010 to 2022)EF2026 / recorded history (block-invariant from 2010) (institutional estimate 60,281.4 GWh) vs. EF2026 / recorded history (block-invariant from 2010) (institutional estimate 70,681.6 GWh)+10,400.2 GWhsame issuer
Capacity, British Columbia: the fastest twelve-year stretch in its own record (2011 to 2023)EF2026 / recorded history (block-invariant from 2005) (institutional estimate 15,123.0 MW) vs. EF2026 / recorded history (block-invariant from 2005) (institutional estimate 18,985.8 MW)+3,862.8 MWsame issuer
Evidence qualifications (8)
Latest source: The Canada Energy Regulator's Energy Future 2026 electricity projections: what every scenario assumes about generation and capacity to 2035 and 2050, held beside the dataset's own recorded history · accessed 2026-07-17

Related on this site

This record shows what an institution published and how its figures compare across versions or with later outcomes. It does not rank institutions or grade their forecasting ability.

This is the current public record for this lineage. See Work with Countability for a commissioned projection-resolution question.

Work with Countability